MOUNT ROYAL PAVILION GOING UP WITH THE HELP OF SEVERAL ASSOCIATION MEMBERS. PROGRESS PHOTOS BELOW!
Updated photos of Pavilion Construction - 10/1/19
Construction Progress Photos Below 3/30/2019
Landscaping sod installed. Electricity on. Bathrooms complete. Trim work in progress. Kitchen items pending. Almost ready for C/O inspection.
Landscaping sod installed. Electricity on. Bathrooms complete. Trim work in progress. Kitchen items pending. Almost ready for C/O inspection.
Construction Progress Report & Photos: 2/27/2019
According the volunteers at the site, the MRAPPOA pavilion is nearing completion and should be ready for the annual BOD meeting dated March 22nd. Current and recently completed activities include:
According the volunteers at the site, the MRAPPOA pavilion is nearing completion and should be ready for the annual BOD meeting dated March 22nd. Current and recently completed activities include:
- Landscaping work. Sod to be delivered March 1.
- Electrical completed.
- Interior and exterior painting complete.
- Bathroom fixtures upcoming.
- All trim work upcoming.
- Plumbing work upcoming.
2017-18 Progress Photos